  "description": "A new ruling in its Timely Energization docket directs PG&E, SCE, and SDG&E to respond to questions arising from Guidehouse's review of the utilities' September 2025 Biannual Energization Reports. All parties may answer the same questions.",
  "path": "/the-energization-quagmire-bad-data-and-big-backlogs/",
  "publishedAt": "2026-06-01T12:30:41.000Z",
  "site": "https://www.calregulatory.com",
  "tags": [
    "ruling",
    "questions",
    "Guidehouse's review",
    "Subscribe now"
  ],
  "textContent": "A new ruling in its Timely Energization docket directs PG&E, SCE, and SDG&E to respond to questions arising from Guidehouse's review of the utilities' September 2025 Biannual Energization Reports. All parties may answer the same questions.\n\n### This post is for subscribers only\n\nBecome a member to get access to all content\n\nSubscribe now",
  "title": "The Energization Quagmire: Bad Data and Big Backlogs",
  "updatedAt": "2026-06-02T05:17:13.661Z"
}