Maryland Pushes Back on $2 Billion Grid Upgrades
Broadband Breakfast
May 11, 2026
WASHINGTON, May 11, 2026 – Maryland officials are challenging an estimated $2 billion in electricity transmission costs that they say are being unfairly shifted onto state residents and businesses.
The Maryland Office of People’s Counsel has filed a complaint with the Federal Energy Regulatory Commission against PJM Interconnection, the regional grid operator serving 13 states and Washington, D.C.
The state argues that PJM’s cost allocation formula improperly requires Maryland ratepayers to subsidize transmission projects primarily driven by data center expansion in other states.